An expert panel of the environment and forests ministry has found that construction of Tezpur Medical College and Hospital has begun without obtaining the mandatory environmental clearances, which is in “violation” of the Environment Impact Assessment Notification.
The issue came up for discussion at the 116th meeting of the expert appraisal committee for building construction, coastal regulation zone, infrastructure development and miscellaneous projects that was held from September 19 to 21 at New Delhi.
“The committee after discussion (has) concluded that since construction has already begun, this is a case of violation,” the committee report stated. According to the details of the meeting, an executive engineer of the public works department revealed that construction for the above project had already begun.
Environmental clearance for certain developmental projects has been made mandatory by the ministry of environment and forests through its notification issued on January 27, 1994 under the provisions of Environment (Protection) Act, 1986.
The issue came up for discussion at the 116th meeting of the expert appraisal committee for building construction, coastal regulation zone, infrastructure development and miscellaneous projects that was held from September 19 to 21 at New Delhi.
“The committee after discussion (has) concluded that since construction has already begun, this is a case of violation,” the committee report stated. According to the details of the meeting, an executive engineer of the public works department revealed that construction for the above project had already begun.
Environmental clearance for certain developmental projects has been made mandatory by the ministry of environment and forests through its notification issued on January 27, 1994 under the provisions of Environment (Protection) Act, 1986.