The non-availability of power evacuation line beyond Silchar has created an obstacle in the commercial run of the first unit (363-MW capacity) of the project.
Officials of ONGC-Tripura Power Company Limited (OTPC) here said Palatana had produced 42 MW of power on October 22, and in two days, its power generation capacity reached to about 72 MW during test run. Very soon, the first unit of the project would be able to generate about 363 MW of power.
"Due to non-availability of power evacuation system up to Bongaigoan, the Palatana project can't produce power as per its capacity. After 120 MW, we have to put a cap on production, as the northeast load dispatch centre is yet to get the transmission nod," a top OTPC official said.